Daily Site Reports
Monitor daily progress, weather logs, and material consumption.
42
Total Submitted
68%
Cumulative Progress
2 hari
Rainy Days Logged
352 sak
Cement Consumed
Sunday, Aug 2, 2026
AMPM
Physical Progress80%
Pengecoran struktur kolom beton BSD Office lantai 2 selesai 80%. Pengiriman besi tulangan 1.5 ton sudah diverifikasi.
Work Activities
- Pengecoran Kolom Lantai 2
- Pemasangan Begesting Besi
Materials Consumed
Semen Portland
45 sak
Pasir Beton
4.5 m³
Besi Tulangan 12mm
150 batang
Reporter: Candra Wijaya
Saturday, Aug 1, 2026
AMPM
Physical Progress100%
Pekerjaan galian pondasi selesai 100%. Dilanjutkan perataan tanah dasar dan penaburan pasir urug setebal 10cm.
Work Activities
- Galian Tanah Pondasi Tapak
- Pemasangan Pasir Urug Tebal 10cm
Materials Consumed
Pasir Urug
12 m³
Air Bersih
2 tangki
Reporter: Candra Wijaya